None of the funds made available in this title may be used to approve critical decision–2 or critical decision–3 under Department of Energy Order 413.3B, or any successive departmental guidance, for construction projects where the total project cost exceeds $100,000,000, until a separate independent cost estimate has been developed for the project for that critical decision.