Early access: 17,112 bills from the current Congress so far, more added daily. Data from Congress.gov, GovInfo and the House and Senate vote records, updated Nov 28, 2026.
Public Law TrackerPLTPublic Law Tracker

H.R. 3632 · Where this bill is now

In the Senate

Passed the House Dec 16, 2025. Received Dec 17, 2025; no Senate vote yet

What this bill does

In plain words · AI-written from the official summary
In plain words · AI-written from the official summary

Would let FERC order power plants to stay open up to five years for reliability

This bill would change how the Federal Energy Regulatory Commission (FERC) decides, on a complaint from a state commission, whether a power plant must stay open because its retirement would make the bulk power system unreliable, and would let transmission organizations also file complaints. If FERC finds that a utility's interstate service is, or is likely within five years to become, inadequate or insufficient, FERC would have to set the proper service by order, and it would be able to order a power plant to stay open for up to five years, with extensions possible on request. The order would have to set any rate or charge needed to pay for the added costs and how those costs are shared. Power plant owners or operators would have to notify FERC and affected state commissions or transmission organizations at least five years before a planned unit retirement, except in an emergency or similar event that makes a unit inoperable, and actions taken to comply with FERC orders would be exempt from federal, state and local environmental laws and regulations.

How it affects you

If this passes, power plant owners and operators would have to give at least five years' notice before retiring a generating unit, except in emergencies, and FERC could order a plant to keep running for up to five years. Any rates or charges FERC sets to pay for the added costs would be shared as its order decides, and actions taken to follow such an order would not be subject to federal, state or local environmental laws.

Read the official summary (Reported to House, Sep 23, 2025)

Power Plant Reliability Act of 2025

This bill modifies the process that the Federal Energy Regulatory Commission (FERC) uses to determine, upon a complaint from a state commission, whether a public utility (i.e., power plant) must remain open because the retirement of the power plant will make the bulk power system unreliable, including by allowing transmission organizations to also file complaints with FERC.

If FERC finds that any interstate service of any public utility is inadequate or insufficient, or is likely to become inadequate or insufficient within five years of receiving such complaint, then FERC must determine the proper, adequate, or sufficient service to be furnished through an order, rule, or regulation (order).

The bill specifies that FERC may order a power plant to remain open for up to five years. Any affected state commission, transmission organization, or power plant may request that FERC extend such order.

A FERC order must determine (1) any rate or charge necessary to provide compensation for the additional costs of the service, and (2) the cost allocation of any rate or charge.

A power plant owner or operator must notify FERC and affected state commissions or transmission organizations at least five years before any planned retirement of a unit of an electric generating facility except in the case of an emergency or similar event that renders a unit inoperable.

The bill exempts from federal, state, and local environmental laws and regulations any action taken by a generating facility to comply with such orders.

Written by AI (Claude) using only the official summary by the Congressional Research Service, the Library of Congress’s nonpartisan research staff. It can miss nuance, so check the official summary and the bill text for details.

119th Congress
1st Session
H. R. 3632

AN ACT

Power Plant Reliability Act of 2025Power Plant

Passed HouseDec 16, 2025 · 222–202In the SenateNo vote yet

Sponsor: Rep. H. Morgan Griffith (R-VA-9) · Introduced May 29, 2025 · Energy · 4 versions of the text

Sources: Congress.gov actions and votes · bill text from GovInfo · latest official action Dec 17, 2025: “Received in the Senate and Read twice and referred to the Committee on Energy and Natural Resources.”

How Congress voted

Official roll calls

House · On Passage · Dec 16, 2025

Passed 222–202

YesNoDidn’t vote
PartyYesNoDidn’t vote
Democrats71997
Republicans21532

10 members voted against most of their party: 7 Democrats voted Yes and 3 Republicans voted No.

Source: Clerk of the House · roll call 342

222–202Passed
DemocratsRepublicans

Congress votes on whole bills and amendments, not on single sections.

Sections

The wording of this bill hasn’t changed across its 4 official versions.

How did H.R. 3632 change?

The text of H.R. 3632 did not change between the Passed the House and Sent to the Senate versions.

Sections · 2