Title III — DEPARTMENT OF ENERGY
Read this section in the full bill →
No wording changed between Passed the House and On the Senate calendar.
How the text changed
None of the funds made available in this title may be used to approve critical decision-2 or critical decision-3 under Department of Energy Order 413.3B, or any successive departmental guidance, for construction projects where the total project cost exceeds $100,000,000, until a separate independent cost estimate has been developed for the project for that critical decision.
None of the funds made available in this title may be used to approve critical decision-2 or critical decision-3 under Department of Energy Order 413.3B, or any successive departmental guidance, for construction projects where the total project cost exceeds $100,000,000, until a separate independent cost estimate has been developed for the project for that critical decision.
added wordsremoved wordsComparison computed by Public Law Tracker from the official text