Title III — DEPARTMENT OF ENERGY
Read this section in the full bill →
No wording changed between Passed the House and On the Senate calendar.
How the text changed
Passed the House → On the Senate calendar · Sec. 304
None of the funds made available in this title may be used to approve critical decision-2 or critical decision-3 under Department of Energy Order 413.3B, or any successive departmental guidance, for construction projects where the total project cost exceeds $100,000,000, until a separate independent cost estimate has been developed for the project for that critical decision.
•HR 4553 PCSSEC. 304