Sec. 3115 · S. 2296

Notification of cost overruns for certain Department of Energy projects

Division C — Department of Energy national security authorizations and other authorizations › Title XXXI — Department of Energy national security programs › Subtitle B — Program authorizations, restrictions, and limitations

Read this section in the full bill →

No wording changed between Committee version and Passed the Senate.

How the text changed

Committee version · Sec. 3115

Section 4713 of the Atomic Energy Defense Act (50 U.S.C. 2753) is amended— (1) in subsection (a)— (A) in paragraph (1)(A), in the first sentence, by inserting prior to entry into Phase 6.3 or Phase 3, as appropriate after Administration; and (B) in paragraph (2)(A), by inserting prior to entry into Phase 6.3 after project; and (2) in subsection (c)(2)— (A) by redesignating subparagraphs (B) and (C) as subparagraphs (C) and (D), respectively; and (B) by inserting after subparagraph (A) the following new subparagraph (B): (B) the results of the review conducted by the Director of Cost Estimating and Program Evaluation are consistent with section 3221(d)(1)(F) of the National Nuclear Security Administration Act (50 U.S.C. 2411(d)(1)(F))..

•S 2296 RSSEC. 3115
Passed the Senate · Sec. 3115

Section 4713 of the Atomic Energy Defense Act (50 U.S.C. 2753) is amended— (1) in subsection (a)— (A) in paragraph (1)(A), in the first sentence, by inserting prior to entry into Phase 6.3 or Phase 3, as appropriate after Administration; and (B) in paragraph (2)(A), by inserting prior to entry into Phase 6.3 after project; and (2) in subsection (c)(2)— (A) by redesignating subparagraphs (B) and (C) as subparagraphs (C) and (D), respectively; and (B) by inserting after subparagraph (A) the following new subparagraph (B): (B) the results of the review conducted by the Director of Cost Estimating and Program Evaluation are consistent with section 3221(d)(1)(F) of the National Nuclear Security Administration Act (50 U.S.C. 2411(d)(1)(F))..

•S 2296 ESSEC. 3115

added wordsremoved wordsComparison computed by Public Law Tracker from the official text